F-35 JSF 개발관련 로이터 통신의 기사 입니다. 앞서 블룸버그 통신은 게이츠 미 국방장관이 2015년까지 계획된 F-35 전투기
도입 물량에서 122대를 취소하고 그 구입 비용 약 28억불을 F-35 JSF 의 개발 및 시험비행 예산으로 전용할 것이라고 보도한
바 있습니다. 이는 현재 JSF 개발과정에서 겪고 있는 여러 문제점들을 예산의 집중지원으로 조속히 해결하고자 하는 대안으로
받아들여지고 있습니다.
아래 로이터 통신의 보도는 이러한 게이츠 국방장관의 결정에 대해서, 제작사 Lockheed Martin 은 국방성과의 의견차가 크지
않으며 향후 개발 일정 역시 순조로이 진행될 것이라는 반응입니다.
사진은 F-35B STOVL 2호기의 공중급유 장면입니다. BF-02 관련 상세사항은 이곳을 참조하시면 됩니다. ---> BF-02 Flight
-------------------------------------------------------------------------------------------------------------------
UPDATE 1-Lockheed says F-35 program not in trouble
Reuters News 01/07/2010
Author: Andrea Shalal-Esa
(C) Reuters Limited 2009.
WASHINGTON, Jan 6 (Reuters) - Lockheed Martin Corp on Wednesday said it was continuing work to sharply reduce the costs of the F-35 fighter and did not believe the program was in trouble despite a report that the Pentagon will cut production of 122 airplanes through 2015.
Lockheed spokesman Chris Geisel said the company was running about four to six months late on finishing the final four of 19 developmental aircraft, which in turn prevented completion of all the flight tests planned by the end of 2009.
But he said the gap was narrowing between Pentagon and Lockheed projections about the cost and time required to complete the development program and the company was continuing its drive to lower overall costs on the program.
"It is Lockheed Martin's intent to continue the ongoing steep reductions in F-35 cost during low-rate initial production so that the government can buy more aircraft within the existing budget," Geisel said.
Concerns about the F-35 program 一 the Pentagon's most expensive weapons program at roughly $300 billion 一 have mounted in recent months, amid declining tolerance by Pentagon officials and lawmakers for cost overruns and schedule delays.
Last month, the U.S. Senate Armed Services Committee said it was "deeply concerned" about the program after a closed-down discussion with Pentagon officials about a strategy to keep costs down and get development efforts back on track.
Air Force Secretary Michael Donley last month told Reuters he expected a shake-up of the F-35 program, including adjustments in schedule, but said there were no plans to reduce the total number of fighters to be purchased.
Lockheed Chief Executive Robert Stevens said his company agreed with the Pentagon that it should use some of its potential profit to get the program back on track.
Senior Lockheed officials were meeting this week with top Pentagon officials to hammer out a final plan for funding the program in fiscal 2011 and the coming years, Geisel said.
"Much of the information that's recently been reported is pre-decisional and we continue to work with the (Office of the Secretary of Defense) to come to resolution," he said.
He said the possible changes being discussed would not affect the U.S. government's plan to buy a total 2,443 F-35s for the three military services, or the dates that the services have set for starting to use the new fighter jets.
"The program is not in trouble. We are a little behind on delivery of the (system design and development) aircraft, about six months, but the rest of the aircraft will be delivered within the next four to six months."
Geisel also noted that the Pentagon was shifting to a more conservative approach when budgeting all weapons programs as a result of an acquisition reform law passed in 2009.
He also noted that Pentagon cost estimators had reduced their estimate of the extra money needed to complete the program's development by $1 billion, and now forecast a delay of just 13 months, about half that initially projected.
Bloomberg on Wednesday reported that Defense Secretary Robert Gates had directed the military in a Dec. 23 budget document to delay the F-35 program, cutting planned purchases by 10 aircraft in fiscal 2011 and a total of 122 through 2015.
Gates cut the purchase of F-35s by 10 planes in 2011 to 42; by 17 in 2012 to 45; by 52 in 2013 to 77; by 20 in 2014 to 90; and 23 in 2015 to 107, it said, citing the document.
Bloomberg said the Pentagon would use more than $2.8 billion that had been budgeted for buying airplanes over those years to continue its development instead.
The money would be used to complete scheduled flight testing more quickly and work on issues such as software, said a source familiar with the program who confirmed the Bloomberg report, but was not authorized to speak publicly.
He said the Pentagon could potentially add back in the production airplanes if Lockheed and the program were able to beat their cost and schedule targets.
Defense analyst Loren Thompson said the Pentagon was essentially putting money back into the development phase of the program that had been removed by the Bush administration, reducing the likelihood of more serious problems later on.
"This really is not bad news for the company. They are shifting money from production to do more test and reduce risk on the program," he said.
"But the government is building incentives into the development program so that some of the production planes taken out might be put back in of the program results are good."
No comment was immediately available from the Pentagon's F-35 office.
F-35B STOVL 2호기가 NAS Patuxent River 로 이동 중 공중급유 받는 장면 (ⓒ Lockheed Martin)
'미국 (USA) > US DoD' 카테고리의 다른 글
F-35 JSF Monthly Assessment Report (October 2009) (0) | 2010.02.23 |
---|---|
미국 장거리 탄도미사일 요격실험 실패, GMD system test failed... (0) | 2010.02.02 |
미 대통령 전용기 에어포스-원 (US Air Force One)... (0) | 2010.01.05 |
미 대통령 전용헬기사업 재추진 계획, US Presidential Helo may again... (0) | 2009.11.30 |
미국 대통령 전용기 에어포스-원, US Air Force One VC-25A.... (0) | 2009.11.24 |